When you take on a building, you take on its lifts: their records, their contracts and the arrangements that keep them safe. Here is what to find, check and act on in your first weeks, with a checklist you can tick off and print.

Durant Lifts engineering teamUpdated 10 min read

Find, check, act.

Taking on a building with lifts means taking on their records and the arrangements around them: who maintains each lift, who examines it, who answers its alarm and who holds its keys. As the dutyholder or their manager, you need to know all of it. Where a lift is used at work, PUWER requires it to be “maintained in an efficient state, in efficient working order and in good repair”, and LOLER requires regular thorough examinations. In a block of flats, HSE says LOLER does not strictly apply, but following it will probably meet the duties that do.

  1. Find the records

    Collect the latest thorough examination report, the maintenance agreement, the service history and the technical documents for each lift, and put copies in one place.

  2. Check the arrangements

    Confirm who examines and maintains each lift, when its next examination is due, who answers its alarm calls and who holds its keys.

  3. Act on what you find

    Put right anything outstanding, starting with defects on the latest report and any examination that is due or overdue.

The checklist at the end of this lesson covers all three steps. If you are not sure who holds which duties for the lifts, start with who is responsible for a lift.

Start with a list of the lifts.

Write down every lift in the building, including platform lifts, goods lifts and service lifts, with where each one is and how it is identified. Each thorough examination report must give “particulars sufficient to identify the lifting equipment”, so use the same name or number as the report, and ask your contractor to use it too.

Note any lift with special features, such as a firefighting lift or an evacuation lift. LEIA’s code of practice asks owners to tell their maintenance contractor about features like these. In a block of flats in England that is at least 18 m high or has at least seven storeys, the responsible person must check lifts for use by firefighters and evacuation lifts every month, record the checks and make the record available to residents. Our lesson on fire safety duties for lifts explains the rest.

Find the records.

A lift’s records are rarely all in one place. Some are with your maintenance contractor, some with the competent person who examines the lift, and some should already be in the building. Gather copies of all of them into one file for each lift.

Where a lift’s records usually areThree places hold the records for a lift, and copies of all of them go into one lift file for each lift. The maintenance contractor holds the service and repair records, the wiring diagrams, which belong to the owner, and the lift phone settings. The competent person holds the thorough examination reports and any examination scheme. The building and the previous manager hold the instruction manual and logbook, the health and safety file, and the keys and special tools.Maintenance contractorService and repair recordsWiring diagrams: yours to keepLift phone settingsCompetent personThorough examination reportsAny examination schemeBuilding and previous managerInstruction manual and logbookHealth and safety fileKeys and special toolsYour lift fileCopies of everything, for each lift
Where a lift’s records usually are. Copies of all of them belong in your own file for each lift.
Describe this diagram

Three places hold the records. The maintenance contractor holds the service and repair records, the wiring diagrams, which belong to the owner, and the lift phone settings. The competent person holds the thorough examination reports and any examination scheme. The building and the previous manager hold the instruction manual and logbook, the health and safety file, and the keys and special tools. Copies of everything go into one lift file for each lift.

The thorough examination reports

Start with the latest thorough examination report for each lift. It must give “the latest date by which the next thorough examination must be carried out”, and it lists any defect that is or could become a danger, with what is needed to put it right. Our lesson on how to read a LOLER report goes through it section by section.

Keep each periodic report until the next one is made, or for two years, whichever is later. If the lift has a report of its examination after installation, keep it for as long as the lift is used where it was installed. If it came with a declaration of conformity, keep that for as long as you operate the lift.

The maintenance records

Ask your maintenance contractor for the service history, including breakdowns and repairs, and for copies of any supplementary test reports. LEIA’s code of practice expects the contractor to give you a record of its maintenance work, and expects you to keep it.

Industry code of practice

“Wiring diagrams /technical information are essential for the safe investigation of faults and such diagrams are the property of the responsible person and not the maintenance company.”

LEIA, LM01 (2013), 5.3

The responsible person in LEIA’s code is usually the lift’s owner or dutyholder. The same code says the owner’s instruction manual is the owner’s property, and that at the end of an agreement documents, drawings, special tools and software access codes go back to the owner, to be kept for the next contractor.

If something is missing

In our experience, records often go missing when a building changes hands or changes managing agent. Ask the previous manager, your maintenance contractor and the competent person for copies. Where the manufacturer’s documents have been lost, LEIA’s code asks owners to try to get replacements from the original manufacturer. Our compliance resources list the documents to keep for each lift.

Check the arrangements.

Records show what has happened. These checks show whether the arrangements for what happens next are in place.

Arrangements to check for each lift
ArrangementWhat to checkWhy it matters
Thorough examinationWho the competent person is, and the latest date on the report for the next examinationLifts that carry people need a thorough examination at least every 6 months, unless a competent person’s examination scheme specifies other intervals. Our LOLER schedule planner turns the date into a schedule.
MaintenanceWho maintains each lift, what the agreement covers, and when it ends or renewsLEIA’s code says a contractor should tell you before an agreement renews automatically. That notice is your chance to review it.
Alarm callsWho answers the lift alarm, what line or SIM it uses, and when it was last testedThe communications link is usually the owner’s responsibility. Analogue phone lines close in January 2027: see the analogue switch-off and lift phones.
KeysWho holds the landing door unlocking keys and the machine room keys, and who may be issued with themKeys that open a landing door or a machinery space give access to serious hazards.
Machine roomsThat machine rooms and machinery spaces are locked and kept clearLEIA’s code says owners should not let them be used for storage or any other purpose.

Landing door keys

A landing door unlocking key opens a landing door even when the car is not there. LEIA’s code of practice says “it is essential that the responsible person only makes the unlocking key available to trained and authorised persons”. Never use one yourself unless you are trained and authorised, and never lend one to cleaners, other contractors or residents.

LEIA, LM01 (2013), 5.8 and 5.10

Act on what you find.

  1. Defects on the latest report

    Agree the repairs with your contractor and the date each will be done. Once the competent person has notified a defect that is a danger, the lift must not be used until it is put right. For a defect that could become a danger later, the report gives the time by which it must be fixed.

  2. An examination that is due, overdue or missing

    Contact the competent person now to arrange it. If nobody examines the lifts, appoint a competent person: choosing the competent person explains what to look for.

  3. A lift your contractor has taken out of service

    Keep it out of service until it has been made safe. LEIA’s code says the responsible person “should not reinstate the plant until sufficient measures have been taken to allow the plant to be returned to service”.

  4. A contract that does not suit the building

    Plan a renewal, a tender or a change of contractor. Our tender checklist helps you compare offers like for like, and our page on switching lift maintenance provider explains how a handover works.

  5. One file for each lift

    Keep copies of every record in one file for each lift, and start a lift logbook so its history stays in one place from now on.

Our view

Deal with safety first: defects on the reports, examinations that are due and the lift alarms. Contracts, files and logbooks matter, but they can follow once you know every lift is safe to use.

Your checklist.

Tick each item as you go, then print the checklist or save it as a PDF. The ticks are not saved anywhere: they last until you close or reload the page.

Taking on a building with lifts

Work through it for every lift. Tick each item when it is done.

Building
Lifts
Date taken on
Checked by
Checklist for taking on a building with lifts
ItemDone
01 Find the records
A list of every lift, named as on its examination report
The latest thorough examination report for each lift
The report of the examination after installation, and the declaration of conformity, where the lift has them
The maintenance agreement, with its start date, renewal date and notice period
Service and repair records, and any supplementary test reports
Wiring diagrams, the instruction manual and the health and safety file
Special tools, software access codes and keys, and who holds each
02 Check the arrangements
Who the competent person is, and the latest date for each lift’s next examination
Any defects on the latest report, and the date each must be put right by
What the maintenance agreement covers, including call-outs and alarm calls
Who answers the lift alarm, what line or SIM it uses and when it was last tested
Landing door unlocking keys kept secure and issued only to trained, authorised people
Machine rooms locked, and not used for storage
Monthly checks of firefighting and evacuation lifts, if the building is a high-rise block of flats in England
03 Act on what you find
Repairs for every defect on the latest report agreed with your contractor, with dates
The next thorough examination booked before its latest date
Missing documents requested from the previous manager, the contractor or the manufacturer
Copies of everything in one file for each lift, and a logbook started
A renewal, tender or change of contractor planned, if the agreement does not suit the building

From Lift Academy by Durant Lifts: durantlifts.co.uk/learn/. Free to copy and use.

Check your understanding.

Three quick questions on this lesson. Choose an answer to check it, or open the answer below each question.

  1. Your maintenance contractor keeps the lift’s wiring diagrams in its office. Who do they belong to?

    1. The maintenance contractor
    2. The lift’s owner, the responsible person
    3. The lift manufacturer
    Show the answer

    B. The lift’s owner, the responsible person. LEIA’s code of practice says wiring diagrams and technical information are the property of the responsible person, usually the owner or dutyholder, and not the maintenance company.

  2. The latest report lists a defect that the competent person says is a danger, and must be put right before the lift is used. What should happen?

    1. The lift can carry on in service until the next maintenance visit
    2. The lift must not be used until the defect is put right
    3. The lift can be used if a warning notice is put up
    Show the answer

    B. The lift must not be used until the defect is put right. Under LOLER, once the competent person has notified a dangerous defect, the dutyholder must make sure the lift is not used until the defect is rectified.

  3. Who should be given a landing door unlocking key?

    1. Anyone on the building staff who might need it
    2. Only trained and authorised people
    3. The cleaners, so they can reach the lift car
    Show the answer

    B. Only trained and authorised people. An unlocked landing door with no car behind it is a serious hazard. LEIA’s code of practice says the key should be made available only to trained and authorised people.

Sources.

The primary sources for this lesson. We checked them when the lesson was last updated on 18 October 2026. How we research and check our lessons.

  1. The Lifting Operations and Lifting Equipment Regulations 1998, regulation 9legislation.gov.uk. Thorough examination before first use, after installation and at regular intervals.
  2. LOLER 1998, regulations 10 and 11legislation.gov.uk. Defects, reports and how long to keep them (regulation 11 follows on the same site).
  3. LOLER 1998, Schedule 1legislation.gov.uk. What a thorough examination report must contain, including the latest date for the next examination.
  4. The Provision and Use of Work Equipment Regulations 1998, regulation 5legislation.gov.uk. The duty to keep work equipment, including lifts, maintained.
  5. L113: Safe use of lifting equipmentHealth and Safety Executive. Approved Code of Practice and guidance on LOLER, including how it applies to lifts in blocks of flats.
  6. LM01: Maintenance requirement for lifts, lifting platforms, escalators and moving walksLift and Escalator Industry Association. Industry code of practice (2013). Section 5 sets out the responsible person’s part, including records, keys and the end of an agreement.
  7. The Fire Safety (England) Regulations 2022, regulation 7legislation.gov.uk. Monthly checks of lifts for use by firefighters and evacuation lifts in high-rise residential buildings.

Taken on a building with lifts?

We can survey the lifts, go through the records you have and tell you what is missing, outstanding or due.

Common questions.

Quick answers to common questions about this topic.

What lift documents should I get when I take over a building?

For each lift: the latest thorough examination report, the report of the examination after installation and the declaration of conformity where the lift has them, the maintenance agreement, the service and repair records, any supplementary test reports, the wiring diagrams, the instruction manual and the health and safety file. Also find the keys, special tools and software access codes, and who holds them.

Who owns the lift wiring diagrams?

LEIA’s code of practice says wiring diagrams and technical information are the property of the responsible person, usually the lift’s owner or dutyholder, and not the maintenance company. Ask your contractor for copies if you do not hold them.

What if I cannot find a current thorough examination report?

Ask the previous manager and the competent person or insurer who examines the lifts for a copy. If nobody is examining the lifts, appoint a competent person and arrange an examination straight away. Under LOLER, lifts that carry people need a thorough examination at least every 6 months, unless a competent person’s examination scheme specifies other intervals.

Who should hold the landing door keys?